2020 Streets Project Information
The 2020 Streets Project will be providing much needed reconstruction and updates to the road along Quality Ave N.
The project will include:
• Pulverizing of the existing street pavement• Installation of storm sewer• Grading in Humphries Park• Driveway and culvert replacement/additions• New pavement• Ditch cleaning and turf establishmentThe project will include the reconstruction of Quality Ave. N from Quamwell Ave. S. to Quality Lane N. (3rd St. S. will be reconstructed in 2021)
This project was scheduled to repair the deteriorating roadway and provide stormwater flooding improvements. The contractor is scheduled to mobilize to the project site on or about Monday April 13th. The project will continue throughout the summer months and updates on the schedule will be provided as available.
2020 Street Project Proposed Schedule
Please note that this schedule is subject to change.
Project wide Quality Ave N - Quality Ave S / 3rd St. S: 85 days Mon 4/13/20 - Fri 8/7/20
Mobilization: 85 Days Mon 4/13/20 - Fri 8/7/20
Traffic Control: 85 Days Mon 4/13/20 - Fri 8/7/20
Saw Cutting: 2 days Mon 4/20/20 - Tue 4/21/20
Reclaim Existing HMA: 1 day Mon 4/20/20 - Mon 4/20/20
Grade Reclaimed material: 2 days Mon 4/20/20 - Tue 4/21/20
Storm Sewer: 20 days Mon 4/20/20 - Fri 5/15/20
Remove/ Replace Culverts: 20 days Tue 4/21/20 - Mon 5/18/20
Common Excavation: 15 days Tue 5/19/20 Mon 6/8/20
Grade Class 5 aggregate: 15 days Fri 5/22/20 - Thu 6/11/20
Concrete C&G: 2 days Fri 6/12/20 - Mon 6/15/20
Fine Grade roadway: 4 days Mon 6/22/20 - Thu 6/25/20
HMA Wearing course lower: 1 day Fri 6/26/20 - Fri 6/26/20
Concrete Driveways: 1 day Mon 6/29/20 Mon - 6/29/20
Ditch Grading: 3 days Tue 6/30/20 - Thu 7/2/20
Raise Adjustments: 2 days Tue 6/30/20 - Wed 7/1/20
Trees: 3 days Thu 7/2/20 - Mon 7/6/20
Erosion Mat & Turf establishment: 3 days Tue 7/7/20 - Thu 7/9/20
Grade Driveways: 2 days Thu 7/2/20 - Fri 7/3/20
HMA Driveways: 2 days Mon 7/6/20 - Tue 7/7/20
HMA Wearing Course Surface: 1 day Wed 7/29/20 - Wed 7/29/20
Shouldering Top Soil/Aggregate: 2 days Thu 7/30/20 - Fri 7/31/20
Shoulder Seeding: 1 days Mon 8/3/20 - Mon 8/3/20
If you have any questions or concerns regarding the 2020 Streets Project please email Simon Wirth at swirth@peopleservice.com or call at 218-491-3575.